M5 work between Wellington and Cullompton costs revealed

The total cost of the work which has closed the M5 for several nights has been confirmed. <i>(Image: Newsquest)</i>
The total cost of the work which has closed the M5 for several nights has been confirmed. (Image: Newsquest)
This article is brought to you by our exclusive subscriber partnership with our sister title USA Today, and has been written by our American colleagues. It does not necessarily reflect the view of The Herald.

NATIONAL Highways has confirmed the total costs of the M5 work, which has contributed to a new upcoming base layer on a section of the motorway.

A section of the M5 at Junction 27 (Willand) is currently being worked on - with concrete repairs being put in place.


READ MORE: Eastwick Road, Taunton, gets petition to reduce speed limit

READ MORE: Taunton M5 exit works delayed by National Highways


Because of this work, several overnight closures have been put in place - including an eight-night M5 closure between Wellington and Cullompton last month.

Works along this road started in Autumn 2024 aiming to finish in Spring 2025, this is believed to still be the case - but has not been confirmed by National Highways since works began.

Speaking about the ongoing motorway work, a spokesperson from National Highways said: "Despite the poor weather in late January 2025, our works to move the contraflow system to the northbound carriageway went well. 

"We now have two lanes running in each direction with all traffic using the northbound carriageway in contraflow. We are now working on the southbound carriageway.

"The works are ongoing and the cost is estimated to be £17.6 million."

The M5 will be closed again from Friday, February 21 between Junction 28 (Cullompton) and Junction 26 (Wellington) for four nights.

Diversions will be in place via the A38 and B3181.

Get involved
with the news

Send your news & photos