MONTHS of roadworks on a major A-road in Somerset have been completed ahead of schedule.
Back in July this year, Somerset Council announced that a large stretch of the A358 Staplegrove Road would be worked on as part of an important utility upgrade and replacement scheme.
The work was planned by Wales and West Utilities (WWU) and National Grid and aimed at replacing ageing gas services and the electrical network along Staplegrove Road and also Minehead Road.
Staplegrove Road is now open and flowing as normal. It follows works which included a one-way system along the A358, operating inward-bound to Taunton only. This led to some frustration for motorists, with usual severe delays reported.
This scheme also includes 'significant improvements' to the Silk Mills junction near the huge Staplegrove West (Quantock Park) development - where there are plans for 713 total homes and commercial units.
Speaking after the road was reopened today (October 9), Councillor Mike Rigby, Lead Member for Economic Development Planning and Assets, said: " I’m pleased to confirm that the developer- and utility-led westbound closure of the A358, Staplegrove has been lifted and the road has reopened today, on time."
The works were initially planned to last a total of 15 weeks and have been completed on time.