A HISTORIC signal box on the West Somerset Railway is undergoing a major overhaul as volunteers work to modernise equipment ahead of the 2027 season.
The railway's 'Signal & Telegraph team' has begun a full replacement of signalling relays and internal wiring at Crowcombe Heathfield signal box, one of the heritage line's key operational sites.
The signal box at the UK's longest heritage railway line was commissioned in May 1994, using the wooden operating floor from Ebbw Vale Sidings and a newly-built brick base.
While the equipment installed at the time has operated reliably for more than 30 years, railway officials decided earlier this year that an upgrade was very much needed.
The Winter project follows the completion of signalling rewiring works at Blue Anchor, with attention now turning to Crowcombe Heathfield.
West Somerset Railway upgrades historic signal box
Work got officially underway in late October after volunteers completed the design of new signalling equipment and wiring systems.
Fortunately, the railway can continue operating trains while the project is carried out, as the signal box can be switched out of use when not required.
With temporary wiring installed to maintain services, engineers have removed the old relays and wiring in preparation for the upgrade.
A new relay cabinet featuring modern railway relays was assembled by volunteers over the summer and will be connected once the new cables and wiring have been installed and terminated.
The railway says the updated system will introduce a number of improvements and bring the signal box in line with current railway signalling practices.
Once installation work is complete, the new equipment will undergo extensive testing by an independent assessor to ensure it is operating safely and correctly before being handed back to the railway's operations team.
The upgraded signal box is expected to return to service in late March, ready for the start of the West Somerset Railway's 2027 operating season.